27-10-2009, 02:51 PM
Taarikh pe Taarikh, Taarikh pe Taarikh pur ’’apartment’’ nahin mila - Mila to sirf Tarikh.’’
Date after Date and Date after Date but didn’t got the apartment. What I got was only Date?
This was one of the famous dialogue of Sunny Deol in Damini movie. Same story gets repeated in real life - There are dates after another date with no sign of Brigade Metropolis possession date.
As per my agreement the apartment was supposed to be delivered by Sept 2007 but now officially the project has been delayed by over two years. Officially it’s two years but technically it’s five years. I booked the apartment in Pre-Launch offer and was informed by Brigade marketing executive that hopefully we will launch the apartment in next 2 months and you should get the apartment in next 2 years. Ok, it was my first apartment and I was a fool who fell into those sugary words.
Last official communication (mail & letter) from Brigade was in Sept 2008 that project has been delayed for 12 months due to shortage of cement, sand and labour. Since then there has been a silence from Brigade Executives and there is no further official clarification as why the Project has been further delayed? Now the forums and word of mouth has become source of ’’official’’ communication channel.
Is shortage of Sand, Cement and labour the real cause of project delay or this has become a habbit of Brigade?
Now let’s explore whether shortage of Sand, Cement and Labour are real cause of delay. It can be partial reasons for the delay may be for few days but certainly not for two years.
If there are real shortage of resources then
1) Why did Brigade started Phase 2 booking?
2) Why did Brigade started booking of commercial areas?
3) Why did Brigade started booking of other projects (Brigade Metropolis, Brigade Petunia, Brigade PalmSprings, Brigade Paramount)?
It’s greed, greed and greed.
If there are shortage of resources then complete projects which you have committed
Date after Date and Date after Date but didn’t got the apartment. What I got was only Date?
This was one of the famous dialogue of Sunny Deol in Damini movie. Same story gets repeated in real life - There are dates after another date with no sign of Brigade Metropolis possession date.
As per my agreement the apartment was supposed to be delivered by Sept 2007 but now officially the project has been delayed by over two years. Officially it’s two years but technically it’s five years. I booked the apartment in Pre-Launch offer and was informed by Brigade marketing executive that hopefully we will launch the apartment in next 2 months and you should get the apartment in next 2 years. Ok, it was my first apartment and I was a fool who fell into those sugary words.
Last official communication (mail & letter) from Brigade was in Sept 2008 that project has been delayed for 12 months due to shortage of cement, sand and labour. Since then there has been a silence from Brigade Executives and there is no further official clarification as why the Project has been further delayed? Now the forums and word of mouth has become source of ’’official’’ communication channel.
Is shortage of Sand, Cement and labour the real cause of project delay or this has become a habbit of Brigade?
Now let’s explore whether shortage of Sand, Cement and Labour are real cause of delay. It can be partial reasons for the delay may be for few days but certainly not for two years.
If there are real shortage of resources then
1) Why did Brigade started Phase 2 booking?
2) Why did Brigade started booking of commercial areas?
3) Why did Brigade started booking of other projects (Brigade Metropolis, Brigade Petunia, Brigade PalmSprings, Brigade Paramount)?
It’s greed, greed and greed.
If there are shortage of resources then complete projects which you have committed